  1. on site ground survey

  2. osc forms

    1. area for installation is ok

  3. prep ground / pallets etc

  4. while base station is being installed, perform RTK mapping flight of area

    1. and setup skippy scout with boundaries/flight routes and flight heights

  5. Place base station, ensure space for drawer to open

  6. place generator cage, install generator and cover

    1. ensure generator exhaust faces cage side (not opening) and that generator access panel faces long side with door

    2. use spare cage door panel to prop open exhaust side cover - attach at bottom and cable tie to cover flap

    3. fuel and oil generator

  7. place battery case

  8. install solar panels

  9. install starlink

  10. connect all wiring and tidy with cable ties

  11. install drone RC

  12. install drone

  13. install 4g router